Package Handling
DCS’s design and engineering team has more than 40 years of experience creating unique parcel handling systems for diverse customer applications. With installations including semi-automated handling in small city distribution centers and fully automated, integrated hubs with advanced conveyor and sorter equipment, DCS routinely thinks outside the box.
E-Commerce and Multi-Channel Fulfillment
DCS designs and implements end-to-end warehouse automation solutions for e-commerce and multi-channel retailers that address numerous workflow challenges. This includes solutions for receiving, putaway, storage, replenishment, order fulfillment, picking, packing, sortation, and outbound shipping. Our custom integrated warehouse, distribution, and fulfillment systems draw from a deep pool of conventional, semi-automated, and automated material handling technologies.
Various Distribution Applications
Whether an operation is considering the construction of a new distribution or fulfillment center, or a retrofit or expansion of an existing facility, it’s important to create a solution that fits the overarching supply chain strategy. DCS has four decades of experience designing and integrating comprehensive, end-to-end material handling solutions that meet a multitude of operational goals. Whether conventional, semi-automated, or fully automated, DCS can help your organization implement a custom solution that meets its goals while maximizing return on investment (ROI).
Supply Chain Consulting
The DCS Supply Chain Consulting team offers a range of services to help your operations address the challenges it faces. Working in partnership with you, DCS consultants analyze your business data- existing workforce, workflow processes, inventory, order data, operations, and more- to determine a strategy that addresses your unique needs. Whether you need an operations assessment, process improvement recommendations, or distribution design services, DCS consultants will help guide you to the material handling system or operational solution that best meets your current and future needs, as well as your budget.
Customer Support
Keeping your warehouse operations and material handling systems running smoothly and at the peak of productivity are the goals of DCS’ Customer Service Team. By partnering with DCS, your warehouse automation solution is supported from commissioning to end of life. You’ll receive comprehensive in-house training of your personnel, including specialized training of your designated internal system expert. Plus, DCS offers a complete package of spare parts and expert system troubleshooting support from qualified engineers dedicated to your installation.
System Design & Integration
DCS offers a broad range of material handling equipment and automated system design, installation, and integration services for a multitude of projects. These include retrofits, expansions, upgrades, and more. While every project is unique, our system design and execution processes are the same, encompassing meticulous attention to detail, frequent communication, and a dedicated partnership with our clients.
About Us
Designed Conveyor Systems (DCS) has 40 years of experience serving major clients in multiple industries by providing material handling, full-scale warehouse operations, and conveyor design solutions that are custom crafted for their needs. DCS does not sell ready-made conveyor systems but builds relationships that empower collaboration to craft custom warehouse designs together. DCS utilizes consulting, engineering design, project management, installation services, and client support to ensure our customers can keep their promises to deliver on time.
Projects
With more than 40 years of experience providing automated system design, installation, and integration services, DCS has created solutions for companies throughout the United States in a broad range of industries and markets. We’ve completed more than 1500 projects ranging from greenfield facilities with completely new systems to expansions and retrofits of existing operations.

5 Tips to Keep Your Installation Project Running Smoothly in the COVID Era

A year ago, I wrote a blog about the importance of communication between suppliers, integrators and customers in order to keep a new material handling installation project on track. Twelve months later, I can share from personal experience that frequent communication among all these parties continues to be absolutely critical in the COVID era to minimizing the risk of disruptions and delays during equipment implementation.

Over the past year we’ve all grown accustomed to the safety measures (temperature checks, health surveys, face masks, social distancing, plus routine sanitization and disinfection of shared tools and vehicles) required by many companies and places of business. Such requirements are no longer disruptive to workflows. Yet, thanks to the coronavirus and its many variants, equipment manufacturing delays persist. Although still lengthy, the timeframes are slightly shorter than before.

Therefore, it has become more important than ever for companies undertaking a greenfield distribution center construction project, or an update or expansion of an existing facility, to have ongoing, frequent communication with original equipment manufacturers (OEMs) and system integrators. This helps to ensure an equipment installation project’s timeline will run as smoothly as possible while minimizing unpleasant scheduling surprises.

Here are a few of my own observations about successful ways to keep your material handling equipment installation on track during the coronavirus pandemic:

1. Buy in bulk. If a company plans multiple facility upgrades or installations – either simultaneously or in close sequence – that will utilize common pieces of equipment from the same supplier, it might make most sense to commission all the equipment at one time. A bulk order often benefits a manufacturer, as they can make several of the same component with one set of tooling before changing over their process to produce the next component. It can also create a stockpile of needed equipment for the customer, shortening delivery times or allowing the integrator more flexibility in sourcing components needed for one project should another one stall.

2. Take inventory. It’s rare, even in non-COVID times, for all the required equipment and components to arrive on time and in the exact installation sequence as planned by the integrator. With current manufacturing lead times continuing to be stretched, having an exacting, precise inventory process in place that documents equipment and components upon receipt is even more critical than it ever was before. If a key item is missing (or arrives damaged) and needs to be replaced, it is important to alert the OEM of the situation. Verify the situation with digital photos of the trailer prior to and after unloading and send those to the supplier immediately in order to have the best chance at keeping the project on schedule. Any delay in discovering and reporting the issue will likely add more days or weeks to already extended delivery and installation timeframes.

3. Be flexible. During the pandemic, the traditional step-by-step, phased installation approach has been particularly hard to follow. If at all possible, it’s best to install the equipment that is there, even if that means completing Phase 1 and skipping to Phase 3 because the Phase 2 components have yet to be delivered. Of course, physical gaps may need to be left open to accommodate any forklifts (or other means of transporting the equipment), as well as for the addition of the missing parts. Likewise, the components that are installed may need to be left partially unfastened in order to make the minute adjustments required to fit the different parts together. But as long as the engineering drawings are correct and precise, it should be possible to continue to install the elements that have been delivered in order to keep the project on track.

4. Provide storage. As noted previously, components and equipment required for a new system installation rarely arrive in alignment with the build schedule. Therefore, if a customer can provide the integrator with a secure storage area to hold received equipment – such as an empty corner of the existing facility, or a separate warehouse on the same campus (or one located nearby) – components can still be delivered and available on-site when needed. This is particularly helpful in a new construction or expansion project. COVID has impacted building timeframes as well, and not every facility is ready for the equipment to be installed upon arrival.

5. Update safety protocols. As the year went on, I noted that several project locations implemented an additional temperature scan of employees and contractors mid-shift, during a lunch break for example. The second temperature check was intended to catch anyone who may develop a fever during the day in order to promptly send them home to take a COVID test and self-quarantine if possible. With a second scan occurring several hours after the first, the idea is to prevent anyone who fell ill from potentially infecting others on site – which could severely impact the project’s progress and timeline.

In my experience over the past year, applying one (or more) of these approaches at different job sites made a critical difference in ensuring that installation projects stayed mostly on schedule. But, as I mentioned at the outset, it’s critical that the integrator and the customer communicate the situation and recommend possible remedies as soon as a threat to the build timeline was identified. Doing so minimized project disruptions and kept progress continuing, even if it wasn’t necessarily in alignment with the original schedule.

Want to learn more about working with DCS on your next facility expansion project? Connect with us.

_

Author

Brian Niccum, Director of Site Management, briann@designedconveyor.com

With 20+ years in the industrial, baggage and material handling industries in both airports and distribution warehouses, Brian has developed and refined an expertise in electro-mechanical conveyance installations. In his career he has worn several hats u2013 from an apprenticeship level to superintendent, and now proudly wears one as our Director of Site Management. Brian has a love for comedies, sports and more importantly his family and 3 bulldogs. They thoroughly enjoy Disney trips as well as spending time at the beach and in the Smokey Mountains.